In Class IV asbestos work, what is commonly done?

  1. Insulation removal

  2. Cleanup of asbestos

  3. Flooring removal

  4. Repair of roofing

The correct answer is: Cleanup of asbestos

In Class IV asbestos work, the primary focus is on cleanup activities involving asbestos-containing materials. This includes tasks such as cleaning up and disposing of asbestos debris and waste that may have been disturbed during construction or maintenance activities. The work performed in this class is generally less invasive than removal or significant handling of asbestos materials, as it emphasizes ensuring that any contamination is safely cleaned up to protect workers and the environment. The distinction of Class IV work lies in its emphasis on maintaining safety and environmental standards through careful cleanup operations, which involves ensuring that areas are free from asbestos exposure after work activities have been completed. This is crucial for preventing health risks associated with asbestos inhalation and ensuring compliance with OSHA regulations.